Hyderabad-based contract development and manufacturing organisation (CDMO), Neuland Laboratories, said it is accelerating a planned expansion of its peptide manufacturing capacity, with the first of four scheduled modules now operational at its commercial peptide manufacturing site.
The company said foundational infrastructure for a second module is already in place and that it expects to begin work on it ahead of its original timeline once customer requirements are finalised. The company revealed that configuration, instrumentation and capacity for that module are currently being defined with the customer whose projects will anchor the expanded capability.
The newly operational first module provides 7,000-litre total reactor capacity, comprising 750-litre solid-phase peptide synthesis (SPPS) and 6,250-litre liquid-phase peptide synthesis (LPPS) capacity. Neuland said this allows it to support customer programmes ranging from small-scale to multi-kilogram quantities of complete peptide active pharmaceutical ingredients, including complex and long-chain peptides, as well as commercial-scale production of crude peptides. The SPPS and LPPS reactors are housed in separate suites to allow parallel operation, and are supported by three dynamic axial compression (DAC) columns — one 45-cm and two 60-cm — along with two lyophilisers of 100-litre and 200-litre capacity.
Following a $30-mn investment in the first module, Neuland said it is aligning further investment for subsequent modules with emerging customer requirements. The planned second module would provide up to 18,000 litres of overall reactor capacity, comprising three 5,000-litre LPPS reactors, either a 1,000-litre or 2,000-litre SPPS reactor, and smaller reactors of up to 1,000 litres, a configuration intended to support a broad range of peptide programmes and production scales.
Neuland said the range of indications it is working across is also broadening beyond obesity and metabolic disease, with oncology emerging as an active area of early-stage development, as growing peptide pipelines put pressure on the availability of outsourced development and manufacturing capacity in the industry.
Mr. Saharsh Davuluri, Neuland’s CEO & MD, said, “Our goal is to ensure we have the capacity to meet customer demand not just over the next 24 months, but over the next decade, as we deepen our strategic partnerships with leading pharma and biotech companies.” The company said it is already exploring options to meet medium-term demand.


18 September, 2026 16:42:29 IST 