BASF said it has started “change negotiations” for its Harjavalta (Finland) precursor cathode active materials plant because of “lengthy permitting process with unclear outcomes leading to an unpredictable timeframe for receiving a final, unappealable permit”.
Change negotiations are a statutory consultation process in Finland with employee representatives that is conducted if an employer is considering potential layoffs or other redundancy measures. The process lasts for six weeks, and any possible measures is decided by the company after the process has been completed.
BASF said it is forced to consider layoffs for an indefinite period, potentially impacting all employees at the Harjavalta site.
The German chemical giant said its Harjavalta operations suffered another setback after the Vaasa Administrative Court cancelled a temporary environmental permit for the plant on February 21, 2024.
“The further postponement of and uncertainty around the formal startup date have long-term financial implications for BASF in Harjavalta. BASF must therefore adapt its operations and manage its costs in order to deal with the current situation,” it informed.
BASF had initially announced the construction of the factory for cathode material precursors in October 2018, with a targeted start of production at the end of 2020. The plant was to be built in the neighbourhood of the refinery of the Russian mining group Norilsk Nickel (Nornickel), as BASF and its partner at the time had already concluded a long-term supply agreement for nickel and cobalt from the metal refinery.
“In 2020, BASF received the first permit from the relevant authorities after an extensive environmental impact assessment. Since then, we have been on a painful journey with several cycles of permits being granted, appealed, and – unfortunately – not upheld,” said Mr. Tomi Oja, Managing Director of BASF Battery Materials Finland Oy. “We are disappointed to have received different signals from authorities and the administrative courts. In a dynamic market like the battery market, which requires major investments, both speed and certainty are essential for business planning. This includes a clear legal framework. We always had high hopes for the site, and we hope that at some time in the future these hopes will be finally realised,” he added.
BASF said it remains committed to driving the expansion of its global battery materials business. “The supply of precursor cathode active materials for BASF’s cathode active materials production in Schwarzheide, Germany, is assured, leveraging a broad portfolio of partner network and market access, and its operations are not affected,” it said.


16 April, 2024 17:11:22 IST 