Grupa Azoty, a major European producer of fertilizers and chemicals, has withdrawn from the Polimery Police project’s Engineering, Procurement, and Construction (EPC) agreement with Hyundai Engineering, citing persistent delays, the failure to meet test run milestones, reaching contractual penalty limits, and an inability to agree on counterclaims.
The Polimery Police project aims to build a propane dehydrogenation (PDH) and polypropylene (PP) plant in Police, Poland. The project is considered the largest investment in the Polish chemical industry.
The Polish chemical company announced the withdrawal on August 14, 2025, and has initiated contractual penalties of approximately €111.8-mn against Hyundai.
According to Grupa Azoty, it had already charged Hyundai Engineering the maximum contractual penalties permitted for the delays