DCM Shriram is seeking to raise the share of renewable energy at its Bharuch site in Gujarat with the signing of a power purchase agreement (PPA) with Serentica Renewables India 38 Pvt. Ltd. for the development of a 58-MW peak hybrid renewable energy power project
The contracted power will be supplied by Serentica Renewables through a 190-MW hybrid renewable energy project combining solar power from Rajasthan and wind power from Karnataka.
As part of the deal, DCM Shriram will invest up to Rs. 105-crore in one or more tranches to acquire a minimum 26% equity stake in Serentica Renewables India 38 Pvt. Ltd.
The project is expected to help avoid nearly 0.4 million tonnes of CO₂ emissions annually, supporting DCM Shriram’s decarbonisation goals while enabling a reliable supply of renewable energy for its operations.
Upon completion, DCM Shriram’s total renewable energy capacity will rise to 176-MW (peak) across it two sites in Bharuch & Kota, significantly expanding its clean energy base. The project is expected to be commissioned by June 2027.
Commenting on the development, Mr. Sabaleel Nandy, Executive Director & CEO, DCM Shriram Chemicals, said, “The agreement is a strategic step in expanding the share of renewable energy across our chemical operations in Bharuch and our ongoing efforts towards making the business more sustainable. Further, given that power is one of the most significant input costs, this will help improve cost efficiency, provide greater visibility into long-term power costs and reduce exposure to fluctuations in conventional energy prices.”


21 July, 2026 15:44:54 IST 