The Board of Directors of DCM Shriram Ltd. have approved investment in projects for making aluminium chloride facility and granulated calcium chloride.
The board gave the green light to a substantial capital expenditure of Rs. 310-crore for setting up the new chemical facilities in Jhagadia, Bharuch, including a 100-tpd (tonnes per day) aluminium chloride facility and a 225-tpd granulated calcium chloride facility. These projects will get commissioned in Q1 FY27 and will ensure a chlorine sink of ~225-tpd, the company said.
During the quarter, the company operationalised its hydrogen peroxide plant, while the epichlorohydrin project is expected to be commissioned by Q4 FY25.
"Commissioning of projects like hydrogen peroxide and epichlorohydrin will provide further stability and strengthen the business. The business will continue to look for new growth opportunities in upstream as well as downstream areas including adjacencies," it said in a presentation.
Strategic expansion into renewable energy
In a significant move towards sustainability, DCM Shriram's board approved multiple strategic investments, including an equity investment of up to Rs. 60-crore for acquiring a 28% stake in Special Purpose Vehicles (SPVs) to establish a 68-MW wind-solar hybrid renewable power project. Additionally, the company sanctioned a capital expenditure of Rs. 23-crore for a renewable power project in Kota, Rajasthan.


12 November, 2024 16:46:54 IST 