BASF starts up butyl acrylate plant at Zhanjiang site; mechanical completion achieved for cracker and petrochemical plants

Article image

Germany’s BASF has announced further milestones at its Zhanjiang Verbund site in China – which represents the company’s largest investment outside of Germany, with a total investment of up to €10-bn upon completion. As a fully backward integrated complex, the site includes a steam cracker with an annual capacity of one million metric tons of ethylene, along with downstream petrochemical plants. These facilities are scheduled to begin operations by the end of 2025

In late July, BASF had announced the successful mechanical completion of the first batch of plants in the acrylics complex at the site, including the glacial acrylic acid (GAA) and butyl acrylate (BA) plants. Now the company has confirmed the successful start-up of the BA plant, which will have an annual production capacity of approximately 400,000 metric tons.

“The butyl acrylate plant commenced operations on August 11, 2025, ahead of schedule and with an exemplary safety record. The first shipment was successfully delivered via tanker trucks on August 17, 2025, marking the plant's inaugural customer delivery,” the company informed.

BASF also announced the mechanical completion of the steam cracker and all downstream petrochemical plants, including ethylene oxide, oxo alcohols, syngas, and high-density polyethylene, at the site, transitioning the project from “construction to operational readiness”. This milestone ensures all systems are installed, connected, and tested, paving the way for commissioning and start-up activities scheduled for the end of 2025, it added.

“With the site on track for start-up by end of 2025, we are well-positioned to fulfil the growing market needs and support our customers’ success with greater efficiency and shorter lead times,” said Mr. Bir Darbar Mehta, Senior Vice President of Petrochemicals Asia Pacific at BASF.

article image
calender image

calender image 9 November, 2026 20:19:59 IST

Will India’s butadiene paradox resolve through integrated C4 value chain development?

India is at an important turning point in the development of its butadiene value chain. For years, the country...
article image

calender image 9 November, 2026 19:59:03 IST

GAIL subsidiary commissions PTA plant at Mangalore

GAIL (India) Ltd. has commissioned a 1.25-mtpa purified terephthalic acid (PTA) plant at the Mangalore Special Economic Zone...

PRINT EDITION

View Past Issues

Search For

Exhibitions & Conferences

ChemExpo IndiaChemProTechChemLogistics India

Watch

KKBangEchemiAPi ChinaGPCA ForumCPHI PMEC INDIA